Relocatable classrooms that meet sustainability objectives

Relocatable classrooms that meet sustainability objectives

Prefabricated Relocatable Classroom

Background

With school space increasingly becoming community space too, Telford and Wrekin Borough Council wanted to explore possibilities for relocatable school classrooms that could serve multiple uses while meeting sustainability objectives. It appointed Integer, a partnership for green and intelligent building, to help formulate a working brief and project manage two separate classrooms through to completion.


Building details

Type of building: Prefabricated Relocatable Classroom
Year of construction/ Floor area: Year: 2003 / floor area: 169 m²
Heating and cooling / measures installed
- The units are highly insulated and designed to use passive solar gain and waste heat from the ICT and the occupants;
- There is no traditional heating system;
- A small amount of under floor heating is installed to pre-heat the building after periods of non-use during cold periods;
- The automatic ventilation units also help conserve the heat.


ProjectDescription

Aim To create prefabricated, modular and multiple-use classrooms that meet sustainability criteria while providing a suitable learning environment.
Key points
Technical Features
- Classrooms have single-point foundations of screw piles, suitable for relocation;
- Each classroom comprises four, 12m long prefabricated modules;
- Eco-Warrior energy monitoring software was installed, and delivers monitoring data to interactive classroom whiteboards;
- As well an increasing insulation levels, low-energy lighting with presence detectors, solar water heating and photovoltaics (more than enough capacity for the lighting, but not enough for IT);
- Perhaps the most evident energy strategy is the building’s section and orientation towards the South;
- The conservatory has a sedum roof with motorised vents and integrated triple wall polycarbonate glazing and roller shutters mounted to the walls while light pipes and wind-catchers bring natural light and ventilation into the depth of the classroom space;
- One of the classrooms is clad with untreated western red cedar while the other is clad with galvanised steel mesh screens, on which plants will be encouraged to grow.
Use
- The classrooms are currently shared by juniors and secondary school students, rather than having a permanent class base;
- The management group plans to avail the separate classrooms to other schools as well as community groups, and to use them as bases for staff training.
Reason for inclusion as Shining Example These classrooms show-piece a rich array of technical features that champion sustainability in buildings, but this Shining Example also demonstrates the role of specialist expertise and community involvement, once the prerequisite leadership from within the Council is established.


- Colour-coded according to time periods
- Profiles can be in units, costs, or demand of energy monitored
- Profiles can be in yearly, quarterly, monthly, weekly or daily data


Costs&Benefits

Costs &
funding
The cost for one classroom, based on the final accounts, for the gross internal area is €2,910m2, for the two–off prototypes, with a view to further batch production.
Benefits Savings in energy and maintenance costs, when compared to traditional construction are estimated at €121/m2/a.


Partners&Roles

Partnership details Partnership was central to the success of these classrooms: Telford and Wrekin brought Integer on board to project manage the developments and to provide technical expertise; Yorkon provided specialist skills in prefabrication, while school students and the wider community were consulted to ensure that features of the building and the building process met with their needs.


Recommendations

Achievements Integer took some time understanding the prefabrication system and the potential to customise standard offerings such as: under floor cabling; background electric heating; ceiling lighting without suspended ceilings; and increased levels of insulation.
Telford and Wrekin are currently evaluating the net benefits of this kind of school building before deciding whether to roll out further variants: whether a market for generously sized prefabricated units (by normally 55m2 standards) can be developed remains to be seen.
Lessons Learned These classrooms perform at least as well as their more conventional cousins in terms of their primary purpose – to provide suitable learning environments; they also meet emerging needs for sustainability and given space constraints, and in addition they suggest new possibilities to other schools.

To know more

Organisation
name
i and i Limited
Contact Alison Nicholl
Phone +44(0)1923665950
Email alison.nichol@iandi.ltd.uk
Website www.iandi.ltd.uk

return to United Kingdom
retour sur Royaume-Uni

return to case studies
retour sur Bonnes pratiques





Zoom


Frankfurt am Main: Small CHP plants provide heat and electricity
Frankfurt’s Carl von Weinberg School is one of 15 buildings involved in a project realised by the City of Frankfurt in 2000. Since, 18 gas fuelled cogeneration plants aliment the buildings with electricity and heat.







Energie-CitésEuropean UnionBanner left
Top


Supported by the European Commission
DG ENV (2003 - 2005) / DG TREN (since 2005)
Website coordinated by Energie-Cités. All rights reserved.